Road and Interchanges on the existing 6th Ring Road to Interchange 82 – Salmi Road, Phase I

RA/259

Road and Interchanges on the existing 6th Ring Road to Interchange 82 – Salmi Road, Phase I

RA/259

Project Brief

The RA/259 Project’s scope of work includes construction, completion and maintenance of Road and Interchanges on the Existing 6th Ring Road to Interchange 82 (Salmi Road, Phase I) Kuwait

5
Roads and Bridges
5
Civil Infrastructure
5
Electro-mechanical

Project Schedule

5
Date of Commencement

29-11-2017

5
Date of Completion

18-05-2022

Scope of Work

5
Project Owner

Ministry of Public Works (MPW) / Public Authority for Roads & Transportation (PART)

5
Consultant

Halcrow – Kuwait Technical Consulting Bureau

5
Contractor

United Gulf Construction Co. W.L.L. in association with Metallurgical Corporation of China Ltd. (MCC)

5
Contract Value
USD 487,150,000 (KWD 149,500,000)

Scope of Work

The RA/259 Project’s scope of work includes construction, completion and maintenance of Road and Interchanges on the Existing 6th Ring Road to Interchange 82 (Salmi Road, Phase I) Kuwait.

The Project’s scope consists of the following main components:

5
Expressways
  • Main 22km Expressway
  • Construction of dual (3-lanes and 4-Ianes) expressways
5
Intersections

Construction of 4 Intersections

5
Bridges
  • Construction of 3 nos. Bridges, and Railway Cross Bridge
  • Bridge Bearings and Expansion joints
  • Post-tensioning and precast Girders.
  • Bridges Drainage works
5
Culverts

Construction of Concrete Box Culverts for KOC pipelines protection

5
Drainage System

Construction of Water pipe lines, and Stormwater drainage

5
Electrical Works
  • Bridge under lighting and OH signage lighting works
  • Street lighting and Cablings works
  • Speed cameras, VMS, ATS reservation and CCTV, and Telephone cabling