A'Seeb Sewage Collection and Conveyance System

Contract 5A(HAYA/E024/2009)

A’Seeb Sewage Collection and
Conveyance System

Contract 5A(HAYA/E024/2009)

Project Brief

A’Seeb Sewage Collection and Conveyance System- Al Khoudh Gravity Sewer Network
5
Civil Infrastructure
5
Micro-tunneling
5
Water and Wastewater Management
5
Project Owner

Haya Water

5
Consultant

Parsons International & Company LLC

5
Contractor

United Gulf Construction Co. W.L.L.

5
Contract Value

USD 151,100,000 (OMR 58,100,000)

5
Year of Completion

2013

5
Country

Sultanate of Oman

Project Details

The Project Contact No 5A is for the construction of the sewerage network and treated effluent transmission and distribution networks in sector 1 and 2 of Al Khoudh area. The Sewage network is designed to receive flow from parts of al khoudh area south of Sultan Qaboos highway, however this contact considers the installation of the lines required to serve the existing plots only.

There were approximately 4,520 numbers of existing plots, the majority of which are used for residential purposes, although there were many types of developments in the area.

The sewage collection networks shall be constructed in UPVC/HDPE pipes. The main trunk sewers discharge into the main collector sewer which serves the whole of the A’seeb catchment area and conveys the flow to the treatment plant. The existing sewerage networks in part of the contract shall be abandoned.

 

5
Scope of Work
A’Seeb Sewage Collection and Conveyance System- Al Khoudh Gravity Sewer Network
5
Project Statistics
  • 104.50 km Main and Lateral Line – Gravity Sever UPVC pipe (Dia 200mm and 250mm)
  • 17.13 km Main and Lateral Line – HDPE pipe (Dia 300mm to 700mm)
  • 209.33 km House connection pipelines – UPVC pipe (Dia 160mm and 200mm)
  • 42.98Km TSE & DS pressure line – HDPE pipes (Dia 160mm to 900mm)
  • 294.27 km FOC ducts – HDPE pipe (Dia 25mm and 110mm)
  • 3,546 Nos HDPE Manholes
  • 258 Nos concrete valve chambers
  • 6,087 Nos HDPE house connection chambers
  • 11,898 Nos Solid Block house connection Chambers
  • 2,879 Nos concrete FOC chambers
  • And related complete earth works and reinstatement of roads and structures