Project Brief

New Effluent Water Transfer Pipelines from GC 17, 27 & 28 to MWIP and GC 28 EWTS and Tankage Up Gradation at West Kuwait
5
Civil Infrastructure
5
Electro-mechanical
5
Oil and Gas
5
Project Owner

Kuwait Oil Company (KOC)

5
Contractor

United Gulf Construction Co. W.L.L.

5
Contract Value
USD 32,140,000 (KWD 9,700,000)
5
Year of Completion

2015

5
Country

Kuwait

Project Details

The work to be carried out includes the complete detailed engineering design, procurement and supply of material, testing, shipping and construction, site inspection, pre-commissioning and commissioning of all the works described in the contract specifications.
5
Project Particulars
  • Survey, Site Verification and Drawings Updates
  • Engineering – modification and replacement design of the existing effluent water pipeline system, HSE related studies HAZOP, PSHER etc.)
  • Instrumentation and Controls Modifications
  • Process, Mechanical & Pipeline Works
  • Electrical works
  • Instrument Works
  • Civil and structural Works – excavations, concrete works for equipment foundations, fencing etc.
  • Miscellaneous Works – Re-routing/Extension of Existing Lines and Services, Road Crossings, Valve Access platforms and new cross-overs, Start-up and Commissioning Spares, HSE Requirements
  • Painting, Insulation and Coating
  • Inspection and Tests
  • Documentation Requirements

The execution of the works shall include supply of Manpower, Equipment, Tools, Scaffolding and other requirements for the full and proper execution of the works, all as per contract specification.