KP3-CNS-301
Construction, Completion, Furnishing and Maintenance of Package No. (3) for Aircraft’s Apron and Taxiways and Service Buildings for the New Passenger Terminal Building (II) at Kuwait International Airport
Project Brief
The KP3-CNS-301 Project’s scope of work includes Construction, Completion, Furnishing and Maintenance of Package No. (3) for Aircraft’s Apron and Taxiways and Service Buildings for the New Passenger Terminal Building (II) at Kuwait International Airport
Building Construction
Civil Infrastructure
Project Description
Project Owner
Ministry of Public Works (MPW)
Consultant
NACO / Gulf Consult
Contractor
LIMAK İNŞAAT SANAYI VE TICARET A.Ş.
Sub-Contractor
United Gulf Construction Co. W.L.L.
Contract Value
KWD 156,150,388
Scope of Work
The KP3-CNS-301 Project’s scope comprises Construction, Completion, Furnishing and Maintenance of Package No. (3) for Aircraft’s Apron and Taxiways and Service Buildings for the New Passenger Terminal Building (II) at Kuwait International Airport
- Building Works – Construction of Central Plant Building & 2 Waiting Buildings.
- Electrical Substation – Construction of Electrical Substation.
- Tunnels – Construction of APM/Baggage Tunnel (ATI), Cargo Tunnel (CT1), Ground Service Equipment (GSE1, GSE2) Tunnels and associated MEP works.
- Jet Fuel Hydrant System – Civil, Mechanical, Piping, Electrical, CP system and Instrumentation & Control Works.
- Aircraft Special Systems – Aircraft Potable Water System, Aircraft Sanitary Sewer Vacuum System, Aircraft Blue Water System.
-
- Visual Docking Guidance System, Exterior Lighting, Apron Flood Lighting, Airfield Lighting & Airfield Ground power Units, Electrical Vehicle Charging Equipment, etc.
- Airfield Signals and Controls.
- Jet blast barriers.
-
- HVAC – Pre-insulated Buried Ducting for Aircraft PCA and Subfreezing Pre-conditioned Air AHU.
- External Works Airside – Taxiways, Services Roads (Primary & Secondary), Aprons, Shoulders, Walkways, Traffic Signals, Pavement Marking and Signages, High Security Fence & Gates and associated Mechanical, Utilities and Electrical Works, Ground Improvement and soil stabilization works.
-
- Asphalt Pavement: 570,000 Tons.
- Concrete Pavement: Area 910,000 m2 (553,100 m3).
-
- External Work Landside – Landscape, Landslide Utilities, RCC Underground Reservoir-West (US1), Underground Reservoir-East (US2) and associated Pumping station and MEP works, Waiting Building (WB1), Waiting Building (WB2), PLG Tank Canopy (LP1), MV Equipment, Road Asphalt Works, Road Marking and Signages, Sanitary Sewer Networks, Microtunneling works, Storm Water Utilities and Fresh Water Pipelines.