+965 2205 4250 ugcc@ugcc.com

Contract B7A-Bausher Network-Main Trunk Sewer & Pumping Station, Oman

OWWSC/T/2460879/2023/C1246/2024

Contract B7A-Bausher Network-Main Trunk Sewer & Pumping Station, Oman 

OWWSC/T/2460879/2023/C1246/2024

 

Project Brief

The OWWSC/T/2460879/2023/C1246/2024 Project’s scope of work includes Construction of Bausher Network-Main Trunk Sewer & Pumping Station, and Road Works
5
Electro-mechanical
5
Micro-tunneling
5
Water and Wastewater Management

Project Schedule

5
Date of Commencement

20-10-2024

5
Date of Completion

20-10-2027

Project Description

5
Project Owner
Nama Water Services (Oman Water & Wastewater Services Co.)
5
Contractor
• United Gulf Construction Co. W.L.L.
5
Contract Value
OMR 21,000,000 (KWD 16,670,000)

Scope of Work

The project’s scope of work for Contract B7A shall include but is not limited to the construction (Supply, Installation & Commissioning) of the following:

  • Gravity Trunk sewer diameter ranging from 700mm to 1200 mm with an approximate length of 3.5 km, including deep gravity sewer.
  • Gravity sewer manholes of approximately 30 units, including deep gravity sewer Manholes.
  • Construction of road crossing (open cut & Trenchless method) and to be completed with all necessary works.

The contractor shall ensure that manholes constructed inside the Wadi or in its proximity are protected and designed to withstand the following:

    • Structural forces resulted from Wadi flows, considering reasonable storm return period.
    • Scouring effects.
    • Instabilities caused by lateral forces (impact of hydrodynamics) or forces due to turbulence and sediment transport.

The contractor shall connect the drainpipe of the washout valve chamber to the existing sewer manhole or newly constructed drain sump associated with pipes, fittings, and all required to complete the work as per Haya standards.

Dual Rising Mains with an inner diameter of 1000 mm with an approximately total length of 6.5 km each, which includes the following:

    • Air valve, Washout and isolation valve chambers
    • Crossover Valve chamber
    • Interconnecting valve chamber with Al Ansab STP
    • Bausher Heights Pumping Station

The work related to the pumping station shall include the following (but not limited to):

    • Procurement and Construction of Administration building pump station, main fuel tank, generator building, guard room, transformer building, workshop & store, generator building complete with all civil, electrical, mechanical, plumbing, firefighting, HVAC, Instrumentation & control, and SCADA works.
    • Supply and installation of flow meter chamber, inlet valve chamber completes with all associated works.
    • Provision for power supply from MEDC source till transformer building (Construction of approximately 2 km long power supply cable network from the existing sub-stations to the pumping station including road Crossings (open cut & NDRC).
    • Construction of boundary wall and landscape works.
    • Construction of access road works.
    • Construction of Retaining wall, Riprap and Site levelling.

 

Gallery